SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 31, 2011
Construction activity on Alpine Boulevard continues on four tracks: setting of vaults, digging the trench for the underground cable, installing cable and preparing for the jack and bore process. Construction activities for the County of San Diego’s Streetscape Improvement Plan and 20A utility undergrounding effort are continuing. As
Continue reading SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 31, 2011
SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 24, 2011
Construction activity on Alpine Boulevard continues on four tracks: setting of vaults, digging the trench for the underground cable, installing cable and preparing for the jack and bore process. Construction activities for the County of San Diego’s Streetscape Improvement Plan and 20A utility undergrounding effort are continuing. As
Continue reading SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 24, 2011
SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 17, 2011
Construction activity on Alpine Boulevard continues on four tracks: setting of vaults, digging the trench for the underground cable, installing cable and preparing for the jack and bore process. Construction activities for the County of San Diego’s Streetscape Improvement Plan and 20A utility undergrounding effort are continuing. As
Continue reading SDG&E SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 17, 2011
SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 10, 2011
Construction activity on Alpine Boulevard continues on four tracks: setting of vaults, digging the trench for the underground cable, installing cable and preparing for the jack and bore process. Construction activities for the County of San Diego’s Streetscape Improvement Plan and 20A utility undergrounding effort are continuing. As
Continue reading SDG&E SUNRISE POWERLINK CONSTRUCTION SUMMARY: August 10, 2011
|
|